Our Portfolio
Sharaftell

Brief
Repairs and replacement work to open storage space, roads, and drains including building demolition
Duration
14 months
Implementation
- Building demolition, to create more space.
- Test and survey the space that the storage can occupy.
- Build a sufficient open storage space and suitable roads.
- Repair and rebuild existing strong buildings
- Creation of new accessible road waterproofing works
- Opening/Commissioning event of new storage space.

Brief
Addition and alteration works with extension to existing single storey factory and office with mezzanine floors
Duration
19 months
Implementation
- There are a total of 5 building blocks and the works included:
- Demolition works
- Micro-Piling works
- Structural steelworks
- New canopy including feature wall
- Architectural works
- External works including drains, car parks and roads
- Mechanical & Electrical Works.

Brief
Repair and replacement work to open space including related roads, drains, and demolition of an existing hostel building. The general site area is over 40,000m2
Duration
14 months
Remarks
Works were handed over in 2 phases to meet the client’s business requirements.
Implementation
- Demolition of existing 2 storey hostel building
- General Site leveling
- New Drainage works
- Storage platform with compacted mill waste.
- New Roads and Trailer parking area (LTA standard)
- Electrical works
Clients